Conducting a full audit of recurring failures across rooms and plant equipment
Identifying root causes linked to valves, actuators and sensor faults
Introducing new isolation valves to allow half of the building to remain active during upgrade procedures
Replacing 80 Stad valves and actuators
Changing several sensors realted to the BMS.
Changing 2x float valves for both make up tanks.
Installing new central plant sensors to stabilise chiller performance
Delivering rectification works in controlled stages to minimise operational impact
Performing shell and tube clean and annode changes for chilled water vessel.
Changing multiple failed controllers and correcting wiring to multiple units resulting from historical works.