7 Aberdeen Street – Construct Services

Complete Refrigeration & Air were brought in to asses the existing equipment and plan out a complete replacement under insurance due to an afterhours fire damage. The extent of the damage meant the mechanical services had to be completely redesigned for installation. This included all new equipment, duct work, cushion head boxes, control systems, pipework, air diffusion and electrical feeds.

Business name

Construct Services

Location

7 Aberdeen Street

Industry

Construction

The Problem

The team started by decommissioning and removing all equipment from site. The new Actron equipment added included; PRV17 | PRV330 | PCG400 | PKY500.
Fire damaged system meant a complete redesign and installation from fresh
Fire damaged materials needed to be handled as hazardous given the condition of site
Crane lift from a busy city location that could not be shut down
Working in with multiple trades to ensure tight dead lines were meet
Timely disposal of materials given site restrictions on loading areas/lay down areas

The Solution

The works were finished in scope, on time with a client that had a great review of our team on and offsite.
Worked closely with builders and engineers to make sure shop drawings, plans and unit selection were all outlined and agreed upon before project start
Early morning starts were actioned to ensure completion of the project and crane lift was completed to minimise interactions with the public and reduce the risk to all involved
Close project management by our experienced team, involving meticulous time keeping and working to defined schedules
Multiple groups work in concert onsite to ensure disposal of old materials was completed on the same day as demolition

The Outcome

The new system delivered a significant functional upgrade over the previous installation, eliminating the need for the supplementary cooling that the original design required.
A new system that was more functional than the previous installed system.
System was a significant upgrade and we were able to avoid the supplementary cooling that was required under the previous design.
Better energy efficiency and no defects or warranty calls from installation.

Let’s Discuss Your Requirements