Works were scheduled in with multiple trades (electricians and hvac technicians) to attend site at the same time
Materials were organised before project start date and freighted to site so all equipment was on hand and available for field staff
JSA and SWMS were utilised to minimise work group interactions and maintain safety onsite
Complete Refrigeration & Air’s commissioning team were involved from the start to reduce the time between installation and operation of equipment. This insured equipment was running prior to students returning to school